The Gardens at Flint Hills Place are coming along right on schedule. The crew is now making up time lost due to
the rain by bringing in thirty workers to do the walls and framing.

The second floor on Buildings #2 and #3 will be completed by next Friday (April 28th.)

The water and sewer systems will also be complete by the end of next week.
The View from Kimball Avenue
The Clubhouse
A View From Flint Hills Place
April 21, 2006