| The Gardens at Flint Hills Construction History Developer: R& J Investments Contractor: Snyder Construction |
| The Gardens at Flint Hills Place is a 48-unit Low Income Housing Tax Credit (LIHTC) development that was constructed on 2.5 acres of excess and unused land previously owned by the City of Manhattan, and part of the Flint Hills Place public housing development operated by the Manhattan Housing Authority. On August 11, 2005 the Manhattan Housing Authority submitted an application to the Special Applications Center of HUD to dispose of the 2.5 acres of land to the Manhattan Area Housing Partnership (MAHP) for $1 to facilitate this development; this request was approved on October 13, 2005. The development is financed through Low Income Housing Tax Credits (LIHTC) in the amount of $3,940,869 ($421,519 Tax Credits which created $3,519,350 in Tax Credit equity), and HOME funds in the amount of $200,000. Kansas State University granted an Easement on their property for construction of an access road to the Gardens development at a cost of $1,000. Ground breaking was in December 2005; the project was completed in December of 2006. |
| On December 29, 2005, Snyder Construction began moving dirt at the Gardens at Flint Hills site. Construction crews began setting foundations in February of 2006. Pictured below are views of the site from January 27, 2006. |




| One of the dilemmas faced by the contractor during construction was finding a lot more rock in the ground than had been expected. Once the rock was removed, crews were able to continue setting foundations and to begin framing the buildings. Below are construction pictures from February and March of 2006. |






| By the end of April, 2006, The Gardens at Flint Hills Place was beginning to take form. Construction crews made up time lost due to rain by bringing in thirty extra workers to do the walls and framing. Below are pictures of the continued progress which had been made. |


| By the end of May 2006, The Gardens was slightly ahead of construction schedule. All buildings had roofs completed and interior work had begun on the clubhouse and office. Pictures below show the progress made at this point. |




| By July, pre-leasing of units had begun. Sheetrocking of unit interiors was started as well as siding of building exteriors. |



| The Gardens at Flint Hills became ready for occupancy in December 2006. Below are pictures of more construction progress and the completed development. |






